Project Milestones and Deliverables

From the 2nd Implementation plan (due dates are in months from start of the project, 1st January 2004):

Automation Component

Id Description Due Date Outcome Progress
D5.1.10 Report on the evaluation/identification of the toolbox functions 24 Report February 2005 joint BIOXHIT/e-HTPX/CCP4 automation workshop (Cambridge); see report at http://www.ebi.ac.uk/msd-srv/docs/bioxhit05_1.html

Data Handling Component

Id Description Due Date Outcome Progress
D5.1.4 Integration of XML Schema for messaging with WP5.2 Project Tracking Database 24 Report  
Ms 5.2.1 Implementation of prototype handler and communication protocols 18 n/a Ongoing work with Wendy & Graeme:
  • 5th April 2005 first attempt to add python handler to XIA code
  • 29th April 2005 second meeting to progress this
Ms 5.2.2 Implementation of prototype project history visualisation tools 24 n/a
  • January 2005 implementation of Project Data Explorer for prototype MySQL database
  • March 2005 implementation of "toy" graphviz-based visualiser for CCP4i project history
D5.2.1 Version 1 of independent project database handler application with well-defined interaction protocols 24 Prototype  
D5.2.2 Evaluation report on the requirements of the database system for storing the data 18 Report
  • 14th June This should be pushed back to October (month 22).
D5.2.3 Specification for Version 1 of the Project Database Handler design 24 Report Ongoing via production of prototype (Ms 5.2.1)
D5.2.4 Integration of Version 1 database handler with CCP4i 36 Report  
D5.2.5 Specification for Version 1 of the Project Tracking Database Design 36 Report  
D5.2.6 Implementation of Version 1 Project Tracking Database Design 36 Report  
D5.2.7 Visualisation Tools integrated with Project Tracking Database 36 Report  

Previous Milestones (1st Implementation Plan)

Retained for historical reasons

Id Description Due date Forecast
Ms 5.2.1 Implementation of prototype handler and communication protocols Month 6 Month 18
Ms 5.2.2 Implementation of prototype project history visualisation tools Month 12 Month 24
D 5.2.1 Independent database handler application with well-defined interaction protocols Month 12 Month 24
D 5.2.2 Evaluation report on the requirements of the database system for storing the data Month 18 Month 18